The timetable for the construction of Phase I and Phase II
We will inform you in detail on the progress of the project Čakovický park and the construction of the individual houses and apartments. We will be glad, if you will, together with us, enjoy each step along the way towards high-quality and comfortable living.
Stage 1 | Phase 3
Stage I | Phase 2
2009
-
November / 2009
legal force of zoning and building placement
2010
-
October / 2010
Opening the sale of phase 1. apartments
building Konvalinka (I), Růže (J), Fialka K)
2011
-
January to March / 2011
the tender for general building contractors
-
April / 2011
selected the general building contractor
-
April to May / 2011
Start of Phase 1 construction, Stage One
building Konvalinka (I), Růže (J), Fialka K)
-
December / 2011
Opening the sale of phase 2. apartments
building Lilie, Mateřídouška (L, M)
2012
-
March to April / 2012
Start of Phase 2 construction, Stage One
building Lilie, Mateřídouška (L, M)
-
August / 2012
Completion of Phase 1
building Konvalinka (I), Růže (J), Fialka K)
Stage 1 | Phase 3
2013
-
January / 2013
approval of Bermanova Street in Čakovický park
-
June / 2013
Start of Phase 3 construction
building Gladiola, Hortenzie (G, H)
-
August / 2013
Opening the sale of phase 3.
building Gladiola, Hortenzie (G, H)
2014
-
July / 2014
Opening the sale of Building N apartments
Stage 2
-
February / 2014
Completion of Phase 2
building Lilie, Mateřídouška (L, M)
-
September / 2014
Start of Building N construction
2015
-
February / 2015
Completion of Stage 1
building Gladiola, Hortenzie (G, H)
-
March / 2015
Opening the sale
building Eukalyptus and Frézie (E, F)
-
April / 2015
Start of building
Eukalyptus, Frézie (E, F) construction
-
September / 2015
Opening the sale
building Cedr and Divizna (C, D)
-
September / 2015
Start of building
Cedr, Divizna (C, D) construction
2016
-
February / 2016
Completion of building Narcis (N)
-
February / 2016
Opening the sale
building Pomněnka and Rakytník (P, R)
-
August / 2016
Opening the sale
building Bazalka (B)
-
May / 2016
Start of building
Pomněnka, Rakytník (P, R)
-
September / 2016
Opening the sale
building Azalka (A)
-
October / 2016
Start of building
Bazalka (B)
-
October / 2016
Start of building
Azalka (A)
2017
-
January / 2017
Completion of buildings Eukalyptus, Frézie (E, F)
-
March / 2017
Opening the sale
building Slunečnice (S)
-
August / 2017
Opening the sale
building Tulipán (T)