The timetable for the construction of Phase I and Phase II | Čakovický park

The timetable for the construction of Phase I and Phase II

We will inform you in detail on the progress of the project Čakovický park and the construction of the individual houses and apartments. We will be glad, if you will, together with us, enjoy each step along the way towards high-quality and comfortable living.

Stage 1 | Phase 3

Stage I | Phase 2

2009

  • November / 2009

    legal force of zoning and building placement

2010

  • October / 2010

    Opening the sale of phase 1. apartments
    building Konvalinka (I), Růže (J), Fialka K)

2011

  • January to March / 2011

    the tender for general building contractors

  • April / 2011

    selected the general building contractor

  • April to May / 2011

    Start of Phase 1 construction, Stage One
    building Konvalinka (I), Růže (J), Fialka K)

  • December / 2011

    Opening the sale of phase 2. apartments
    building Lilie, Mateřídouška (L, M)

2012

  • March to April / 2012

    Start of Phase 2 construction, Stage One
    building Lilie, Mateřídouška (L, M)

  • August / 2012

    Completion of Phase 1
    building Konvalinka (I), Růže (J), Fialka K)

Stage 1 | Phase 3

2013

  • January / 2013

    approval of Bermanova Street in Čakovický park

  • June / 2013

    Start of Phase 3 construction
    building Gladiola, Hortenzie (G, H)

  • August / 2013

    Opening the sale of phase 3.
    building Gladiola, Hortenzie (G, H)

2014

  • July / 2014

    Opening the sale of Building N apartments

Stage 2

  • February / 2014

    Completion of Phase 2
    building Lilie, Mateřídouška (L, M)

  • September / 2014

    Start of Building N construction

2015

  • February / 2015

    Completion of Stage 1
    building Gladiola, Hortenzie (G, H)

  • March / 2015

    Opening the sale
    building Eukalyptus and Frézie (E, F)

  • April / 2015

    Start of building
    Eukalyptus, Frézie (E, F) construction

  • September / 2015

    Opening the sale
    building Cedr and Divizna (C, D)

  • September / 2015

    Start of building
    Cedr, Divizna (C, D) construction

2016

  • February / 2016

    Completion of building Narcis (N)

  • February / 2016

    Opening the sale
    building Pomněnka and Rakytník (P, R)

  • August / 2016

    Opening the sale
    building Bazalka (B)

  • May / 2016

    Start of building
    Pomněnka, Rakytník (P, R)

  • September / 2016

    Opening the sale
    building Azalka (A)

  • October / 2016

    Start of building
    Bazalka (B)

  • October / 2016

    Start of building
    Azalka (A)

2017

  • January / 2017

    Completion of buildings Eukalyptus, Frézie (E, F)

  • March / 2017

    Opening the sale
    building Slunečnice (S)

  • August / 2017

    Opening the sale
    building Tulipán (T)